Classroom Installation Process
13 November

Classroom Installation Process

There are various processes that we take to make these classes what they are today. Out of intensive research, careful engineering and brilliant innovation strategies prepared by our team, we seek to provide a quality and affordable solution to schools and a great learning environment to every child.

Take a look at what we do.

Foundation

process (1)

It takes two weeks for the pillars to cure. In the mean time the containers are painted and prepared according to the customised preferences colours and other requirements of the client.

.

 

 

 

 

 

 

 

 

Installation

process (2)

Containers are fabricated in a controlled environment then they’re transported on 18 wheeler trucks to the site.

 

 

Fittings and Adjustments On Site

process (3)

The fabricated containers are installed using a crane and it takes a few hours to put them in place.

.

 

 

 

 

 

Finished Classrooms

process (4)At this stage the windows, flooring, blackboards and stairs are installed on site.

-The whole process takes about three weeks for a full installation